IMPROVEMENT CONTRACTS                                                     H.B. 6197: FLOOR ANALYSIS

 

 

 

 

 

 

 

 

House Bill 6197 (as reported without amendment) Sponsor: Representative James M. Middaugh House Committee: Local Government

Senate Committee: Economic Development, International Trade and Regulatory Affairs

 

CONTENT

 

The bill would create a new act to require a contract between a contractor and a governmental entity for improvements exceeding $75,000 to contain the following provisions:

 

--  The contractor promptly would have to notify the governmental entity in writing if he or she discovered that 1) a subsurface or a latent physical condition at the site was differing materially from those indicated in the improvement contract, and/or 2) an unknown physical condition at the site was of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

--  If the governmental entity received such a notice, it promptly would have to investigate the physical condition.

--  If the governmental entity determined that the physical conditions did materially differ and would cause an increase or decrease in costs or additional time needed to perform the contract, it would have to put its determination in writing. Further, an equitable adjustment would have to be made and the contract modified in writing accordingly.

--  The contractor could not make a claim for additional costs or time because of a physical condition unless he or she had provided the required notice. The governmental entity could extend the time required for notice.

--  The contractor could not make a claim for an adjustment under the contract after he or she had received the final payment under the contract.

 

If an improvement contract did not contain these provisions, they would have to be incorporated into and considered part of the improvement contract. If a contractor did not agree with the governmental entity’s determination, he or she, with the consent of the governmental entity, could complete performance on the contract. The bill also provides for arbitration of a contractor’s entitlement to recover the actual increase in contract time and costs incurred because of the physical condition of the improvement site.

 

The bill would take effect July 1, 1997.

 

Legislative Analyst: L. Burghardt

 

FISCAL IMPACT

 

The bill would have an indeterminate impact on the State and local units of government. It could reduce conflicts regarding physical conditions at construction sites that differ materially from the contract. The Michigan Department of Transportation currently uses a similar clause in its contracts.

 

Date Completed: 12-6-96                                                                   Fiscal Analyst: B. Bowerman

 

 

floor\hb4957

 

This analysis was prepared by nonpartisan Senate staff for use by the Senate in its deliberations and does not constitute an official statement of legislative intent.