HOUSE BILL No. 5799

 

September 16, 2014, Introduced by Rep. McMillin and referred to the Committee on Transportation and Infrastructure.

 

     A bill to amend 1980 PA 524, entitled

 

"An act to provide for the terms of certain construction contracts

with certain public agencies; to regulate the payment and retainage

of payments on construction contracts with certain public agencies;

and to provide for the resolution of certain disputes,"

 

by amending section 2 (MCL 125.1562).

 

THE PEOPLE OF THE STATE OF MICHIGAN ENACT:

 

     Sec. 2. (1) The A construction contract shall designate do

 

both of the following:

 

     (a) Contain specifications that comply with subsection (5).

 

     (b) Designate a person representing the contractor who will

 

submit written requests for progress payments, and a person

 

representing the public agency to whom request for progress

 

payments are to be submitted. The written requests for progress

 

payments shall be submitted to the designated person in a manner

 

and at such times as provided in the construction contract.

 


     (2) The processing of progress payments by the public agency

 

may be deferred by the public agency until work having a prior

 

sequence, as provided in the contract documents, is in place and is

 

approved.

 

     (3) Each progress payment requested, including reasonable

 

interest if requested under subsection (4), shall be paid within 1

 

of the following time periods, whichever is later:

 

     (a) Thirty days after the architect or professional engineer

 

has certified to the public agency that work is in place in the

 

portion of the facility covered by the applicable request for

 

payment in accordance with the contract documents.

 

     (b) Fifteen days after the public agency has received the

 

funds with which to make the progress payment from a department or

 

agency of the federal or state government, if any funds are to come

 

from either of those sources.

 

     (4) Upon failure of a public agency to make a timely progress

 

payment pursuant to this section, the person designated to submit

 

requests for progress payments may include reasonable interest on

 

amounts past due in the next request for payment.

 

     (5) A public agency shall not enter into a construction

 

contract unless it contains bid specifications that meet all of the

 

following requirements:

 

     (a) The bid specifications are written by the architect or

 

professional engineer, designer, or draftsman who provides design

 

services or writes specifications, directly or indirectly, for

 

materials to be used in performing the construction contract. The

 

person who writes the bid specifications shall not be an employee

 


or representative of a manufacturer of any material to be used in

 

performing the construction contract.

 

     (b) Subject to subdivision (c), the bid specifications include

 

performance standards for the materials to be used in performing

 

the construction contract.

 

     (c) If it is impossible or impractical to specify performance

 

standards under subdivision (b), the bid specifications meet all of

 

the following requirements:

 

     (i) List 3 or more examples of materials that establish a range

 

for an acceptable material of similar or equivalent performance

 

characteristics. The materials listed as examples shall be produced

 

by different manufacturers whose ownership is completely

 

independent of each other. If 3 or more materials meeting the

 

requirements of this subdivision are not available, then as many

 

materials meeting these requirements as are available shall be

 

listed.

 

     (ii) State that a material is not required to be manufactured

 

by a specified manufacturer, which is identified only to denote the

 

performance standard for the material, and that equivalent

 

materials are acceptable.

 

     (d) The bid specification do not designate 1 or more preferred

 

manufacturers unless the specifications also identify the

 

performance standards that support the preference. A material that

 

meets the performance standards specified for a designated,

 

preferred manufacturer is considered equivalent to the material

 

from a designated manufacturer.